Revised -
ü
Friday
September 28th 2007
Update model with 2005 demographics, run model, calibrate model, produce model outputs. Draft TIP submitted to TDOT;
ü
Thursday,
October 11th 2007
Comment period on Public Participation Plan ends and adopt the plan within the next week depending on MTPO meeting schedule;
ü
Friday, October 19th 2007
Update plan document with new data and outputs from model and revise all plan documentation for submittal to TDOT for review;
ü
Friday,
November 9th 2007
MTPO Travel Demand Model Approved for Use by TDOT
ü Tuesday, November 13th 2007, revised draft sent to TDOT with response to comments.
ü
Friday,
December 7th 2007
TDOT completes review of LRTP 2nd Draft with minor comments. MTPO
ü
Friday,
December 14th 2007
LRTP delivered to FHWA and FTA for review. (1 month review period).
1. Public Review Period - 1 month mandatory.
2. Adoption of LRTP – early 2008
*note: This schedule was revised due to associated work required in update the Travel Demand Model. This update required new 2005 population estimates and associated data (traffic counts, employment data, etc.) be collected and the model to be recalibrated. After this new forecasts developed and incorporated into the LRTP. This schedule will be updated as each task is completed.